A Solution for Leaky Ductwork

Harvard University

Leaky ductwork connected to a new air handling unit in Girguis Lab at Harvard University was fixed with a new approach to duct sealing.

At Harvard University’s Girguis Lab, engineers had just installed a new 8,500 CFM air handling unit that was meant to supply heat to the lab and an adjacent facility. When the unit was brought online, however, its fan was operating at around 97 percent of capacity with little effect—and that was even before the system was connected to the adjacent facility. It was determined that leaks in the ductwork were reducing static pressure to such a degree that air couldn’t reach its destinations. With ducts hidden under insulation and behind layers of pipes, fixing those leaks seemed an impossible task.

Fortunately, the mechanical contractors on the job had heard about a new approach to duct sealing called Aeroseal that worked from the inside of the air shafts to locate and seal leaks.

In just a matter of days, the problem was fixed. The system’s duct leaks were quickly reduced from more than 5,800 CFM down to 429 CFM—a 98-percent reduction. The AHR fan now operated at only 37 percent of capacity. The system was quieter, and university engineers were relieved.

“I would absolutely call this a project saver,” says John Holliser, senior capital project manager for Harvard. “Our only other option was to tear down walls and demolish the building structure in order to access the leaky ductwork. We were very pleased with the results and I honestly don’t know how we would have solved this issue if the Aeroseal technology wasn’t available.”

aeroseal.com

This article originally appeared in the College Planning & Management July/August 2019 issue of Spaces4Learning.

Featured

  • College of the Mainland Starts Construction on New Library & Learning Center

    College of the Mainland in Texas City, Texas, recently held a groundbreaking ceremony for its new Library & Learning Center, according to a news release. The new facility is part of a larger, $250-million campus expansion project funded by a 2023 bond program.

  • Gretna East High School

    Gretna East High School

    Established in 1999, the Education Design Showcase is a vehicle for showing off innovative — yet practical — solutions in planning, design, architecture, and construction. Gretna East High School has been recognized with an EDS 2025 Project of Distinction award in the category of New Construction.

  • Schools In Focus: Talking Campus Security with Mitch McKinley

    Furnishing the Future: Adaptive Solutions for Modern Learning Spaces

    On this episode of Schools in Focus, we'll talk about the role that classroom furniture plays in creating adaptive, flexible learning spaces. Our guest is Wesley Edmonds, the Director of Workplace, Adaptive Solutions at OFS.

  • Greenheck Receives Sourcewell Cooperative Contract

    Air movement, control, conditioning, and distribution equipment solutions provider Greenheck recently announced that it has been awarded a Sourcewell cooperative purchasing contract, according to a news release. The HVAC Systems contract will allow Greenheck the opportunity to expand opportunities in government procurement and other public agencies in North America.

Digital Edition